Client:
Chicago Public Schools (CPS)
Project Name:
Security Cameras, Bid Packages A, C & F
Chicago, IL
Start/Scheduled Date of Completion Date:
June 2013 - July 2013
Project Scope:

Collectively, these three projects involved 19 elementary schools, four middle schools, and three high schools, installing 310 cameras with work proceeding on multiple sites simultaneously. Work was started and completed in fewer than 30 days.

The scope of work began with the rough-in of the raceways and boxes. After the wire was pulled and the trim was installed, the CCTV and Aiphone intercom equipment was installed. Punch list and final completion was delivered well before the start of the new school year.

Project Dollar Value:
$2,465,500.00
Prime Contractor/Subcontractor:
Prime Contractor